Obsolete PLC migration

Many plants still run on an S7-300, an S5 or another obsolete PLC that is no longer sold. They work well, but spare parts are getting harder to find, and if one fails, it can mean a major production shutdown.

We migrate these PLCs to current models: Siemens S7-1500 or S7-1200 with TIA Portal. If the plant prefers to stay with the same brand, Schneider PLCs move to Modicon M340 or M580 and Omron PLCs to the new CJ3M. We replace the PLC, the screens and the communication network, including in ATEX zones, and hand over the documented program.

We make the changeover in one go, during a long plant shutdown, or step by step: we split the migration into smaller changes and use short production stops. Either way, the program and the screens have already been tested and validated with your team. We work for plants with their own maintenance or engineering team, and we prepare every migration well in advance. At FMJ Ingenieros we have been programming Siemens PLCs since 2007. We backed Siemens from the start, and it was the right decision.

On this page: Status of each PLC · Obsolete networks · How we migrate · Projects · Frequently asked questions · Contact

Is your PLC discontinued?

Status of the most common families, according to each manufacturer's end-of-life notices (October 2026). Each PLC links to its section further down.

BrandPLCStatusWe migrate it to
SiemensS7-300 and ET 200MSold only as a spare part since October 2025. Siemens expects to supply spare parts until October 2033, without guaranteeing this for every moduleSiemens S7-1200 or S7-1500
SiemensS5No Siemens spare parts or repairs since October 2020Siemens S7-1200 or S7-1500
SchneiderModicon TSX PremiumWithdrawn from sale at the end of 2018; service ends at the end of 2026, and has already ended for some CPUsModicon M340 or M580, or Siemens S7-1500
SchneiderModicon QuantumCPUs withdrawn from sale in 2018. Service for Unity CPUs ends at the end of 2027; for the oldest ones it has already endedModicon M580 or Siemens S7-1500
SchneiderTSX MicroWithdrawn from sale at the end of 2019; service until the end of 2027Modicon M340 or Siemens (S7-1200 or S7-1500)
OmronCQM1, C200H and CPMNo longer manufactured; no repairs for the CQM1 since 2019Omron CJ3M or CJ2M, or Siemens S7-1500
OmronCS1 and CJ1CS1: last shipments in Europe in March 2026. CJ1M: withdrawn from sale; repairs until 2028Omron CJ3M or CJ2M, or Siemens S7-1500
Allen-BradleyPLC-5, SLC 500 and MicroLogixWithdrawn from sale between 2017 and 2024 (except the MicroLogix 1400)Siemens S7-1500
MitsubishiA series, FX2N and Q seriesA series and FX2N: CPUs no longer manufactured or repaired. Q series: many CPUs are no longer sold and the rest can be ordered until September 2029Siemens S7-1200 or S7-1500

Sources: Siemens (S7-300, S5), Schneider (Premium, Quantum, TSX Micro), Omron (CQM1, CS1, CJ1M), Rockwell (PLC-5, SLC 500, MicroLogix) and Mitsubishi (A series, FX2N, Q series).

When is the right time to migrate? Before the PLC fails. That way the migration is prepared in good time and the changeover is made during a scheduled plant shutdown. Write to us and we will plan it with you.

Obsolete communication networks

When a PLC becomes obsolete, its network usually does too. These are the networks we find most often in plants, with their status in October 2026.

BrandNetworkStatusWe move it to
SchneiderModbus PlusPremium and TSX Micro card: withdrawn from sale in 2018; service until the end of 2026. Quantum adapter: withdrawn from sale in 2023; service until the end of 2030Ethernet (Modbus TCP) or Profinet
SchneiderFipio, Fipway and Uni-TelwayNetworks of the Premium and TSX Micro, already withdrawn from sale. Fipway card: withdrawn from sale at the end of 2019Ethernet (Modbus TCP) or Profinet
OmronSYSMAC LINKC200H: out of production since 2017. CS1: last shipments in March 2026, with no Omron replacementEtherNet/IP or Profinet
OmronController LinkPC cards: last shipments in March 2025. Omron recommends moving to EtherNet/IPEtherNet/IP or Profinet
OmronCompoBus/SMaster units withdrawn from sale in 2022; repairs until the end of 2029EtherNet/IP or Profinet
Allen-BradleyDH+ and Remote I/OWithdrawn from sale: the ControlLogix DH+ and Remote I/O modules (2024 and 2025), the DH+ PC card (2022) and the SLC 500 Remote I/O scanner (2024). A USB adapter to connect a PC to DH+ is still on saleProfinet
Allen-BradleyDH-485SLC 500 network. Rockwell no longer sells any of its interfaces: the last one, the USB converter for PCs, was withdrawn from sale in 2024Profinet

Sources: Schneider (Modbus Plus, Fipway), Omron (SYSMAC LINK, Controller Link, CompoBus/S) and Rockwell (DH+ and Remote I/O, DH-485).

Siemens SIMATIC S7-1500 PLC with I/O modules in a control panel
The S7-1500 that replaced the TSX Premium PLCs at a chemical plant in the Vallès Oriental.

S7-300 to S7-1500 or S7-1200 migration

We migrate S7-300 CPUs, from the 312 to the 319, including the 314C-2 DP, 315-2 DP, 315-2 PN/DP and 317-2 PN/DP, to S7-1500 or S7-1200. The program moves from STEP 7 to TIA Portal. WinCC flexible screens move to WinCC in TIA Portal or to WinCC Unified, Siemens' current generation, which we have already used on several projects. In the frequently asked questions we explain how long S7-300 spare parts will be available and how long the plant has to stop for the migration.

An S7-300 with Profibus at a pharmaceutical plant in the Vallès Occidental was migrated to an S7-1500 with Profinet. In pharmaceutical plants, the migration includes the validation documents (URS, IQ and OQ), and we apply GMP and 21 CFR Part 11 requirements.

S5 to S7-1500 or S7-1200 migration

With an S5, if a CPU or a card fails, only second-hand spare parts are left. We connect to the PLC with the S5 programming tools and extract the whole program. Then we migrate S5-90U, S5-95U, S5-100U, S5-115U, S5-135U and S5-155U PLCs to S7-1500 or S7-1200, convert the program from S5 to S7 and then to TIA Portal, and replace the operator panels.

At a metal foundry in the Vallès Occidental we replaced an S5 and its operator screen with an ET 200SP CPU, which works like an S7-1500, and Siemens screens. At a plastics extrusion plant in Osona, the S5 and the S7-300 were migrated to an S7-1200.

While we prepare the migration, we can connect to the S5 remotely, with an S5-to-Ethernet converter, to look at the program and see how the installation works.

Schneider PLC migration: TSX Premium, Quantum and TSX Micro

Stay with Schneider or move to Siemens? Staying with Schneider is simpler, and it is what we recommend if the plant does not need changes or expansions. In that case, the TSX Premium (TSX P57 processors) moves to Modicon M340 or M580, the Quantum (140 CPU) to M580 and the TSX Micro (TSX 37) to M340, with EcoStruxure Control Expert (formerly Unity Pro). If the installation needs to be expanded or changed, or the PLC connected to other systems, we recommend moving to Siemens S7-1500 or S7-1200.

The Premium and the TSX Micro usually run Fipio, Fipway, Uni-Telway or Modbus Plus, and the Quantum, Modbus Plus. The Modbus Plus card for the Premium and the TSX Micro was withdrawn from sale in 2018 and its service ends at the end of 2026; to move from Modbus Plus to Ethernet, Schneider now recommends another manufacturer's gateway. We replace these networks with Ethernet using Modbus TCP or, if the PLC moves to Siemens, with Profinet.

At a chemical plant in the Vallès Oriental we have taken both paths: in some panels we migrated several TSX Premium and TSX Micro PLCs to M340, and in another, to S7-1500. With the move to M340, programming went from PL7 to EcoStruxure Control Expert.

Control panel with a TSX Premium PLC before the migrationBefore
The same panel after the migration, with a Modicon M340 PLC and its modulesAfter
The same panel before and after replacing a TSX Premium with a Modicon M340.
Control panel with a TSX Micro PLC and the old wiring before the migrationBefore
The same panel after the migration, with a Modicon M340 PLC and tidy wiringAfter
The same panel before and after replacing a TSX Micro with a Modicon M340.
Control panel with two TSX Premium racks before the migrationBefore
The same panel after the migration, with a Siemens S7-1500 PLC in place of the two racksAfter
The same panel before and after replacing the TSX Premium racks with a Siemens S7-1500.

Omron PLC migration to CJ2M, CJ3M or Siemens

For older Omron PLCs, such as the CQM1 and CQM1H, the C200H and C200HS, the CPM, the CS1 or the CJ1, we offer two routes. If the plant does not need new functions, the simplest option is to stay with Omron and move to the new CJ3M, which replaces the CJ2M. We can also migrate to a CJ2M, which Omron will continue to sell until 2027. If the installation is going to grow or must communicate with other systems, it is better to move to Siemens S7-1500.

Many of these installations use SYSMAC LINK, Controller Link or CompoBus/S, which are running out of support. SYSMAC LINK cards for the C200H stopped being manufactured in 2017; those for the CS1 were supplied until March 2026, and Omron offers no replacement. CompoBus/S master units were withdrawn from sale in 2022, and repairs remain available until the end of 2029. And for Controller Link, Omron no longer makes the PC cards and recommends moving the network to EtherNet/IP. When we migrate the PLC, we move these networks to EtherNet/IP or Profinet.

A waste treatment plant in the Baix Llobregat had two old PLCs communicating with each other over PC Link: a C200HG with two racks and 18 modules, and a CQM1 with 10 modules. We unified the whole installation in a single CJ2M with three racks, removed the communication between the two PLCs, and the final solution was simpler and more reliable.

At the same plant we also migrated another C200H to Siemens, with an ET 200SP CPU with 312 signals: 176 digital inputs, 96 digital outputs and 40 analogue signals, 8 of them with HART. On the front of the new cabinet we installed a 15.6-inch panel PC with Ignition SCADA, which stores a week of historical data. And in the filter press area we replaced a CQM1 with another ET 200SP CPU, with 66 signals in use and spare capacity for expansion: the PLC now controls the drive speeds directly and is integrated into the plant SCADA.

Filter press panel at a waste treatment plant before the migration, with the Omron CQM1 PLC and its modulesBefore
The same panel after the migration, with the Siemens ET 200SP CPU, its I/O modules and the relaysAfter
The same filter press panel before and after replacing the Omron CQM1 with the Siemens ET 200SP CPU.

At a metal foundry in the Anoia we migrated a CQM1 to S7-1500, and a C200H to a CJ2 with Profibus, Profinet and Siemens ET 200S distributed I/O. The second was an easy intermediate step: the move to a newer Omron was quick, and later the CJ2 can be replaced with a Siemens PLC without touching the wiring, by changing only the CPU, because all the I/O runs over Profinet.

Allen-Bradley to Siemens migration

Our preferred route for PLC-5, SLC 500 (SLC 5/03, 5/04 and 5/05) and MicroLogix PLCs is Siemens S7-1500, with the program rebuilt in TIA Portal from the original RSLogix 5 or RSLogix 500 program. If the plant wants to stay with Allen-Bradley, we can do that too.

PLC-5 and SLC 500 PLCs usually run DH+, Remote I/O or DH-485, and Rockwell has stopped selling almost all the components of these networks: the ControlLogix DH+ and Remote I/O modules, the DH+ PC card, the SLC 500 Remote I/O scanner and all DH-485 interfaces. When the PLC moves to Siemens, we replace them with Profinet.

An SLC 5/05 with an Omron screen at a metal foundry in the Anoia was migrated to an S7-1500 with Profinet and a Beijer screen. We chose Beijer because all the screens at the plant are Beijer; we adapt to what each customer has.

Mitsubishi, IDEC and other PLCs

We migrate Mitsubishi A series, FX2N and Q series PLCs to Siemens S7-1200 or S7-1500, as well as IDEC and other older PLCs.

At a water treatment plant in the Vallès Oriental we migrated an IDEC PLC to S7-1200.

Do you need to migrate any of these PLCs? If you are preparing next year's budget or shutdowns, write to us in good time and we will prepare the migration and the schedule with you.

How we migrate

  1. Data collection. We gather all the information about the installation: the electrical diagrams, the current programs, including paper printouts with their comments, and photos of the PLCs, the screens and the rest of the installed equipment.
  2. Validation of the installed program. We check that the program we have is the one running in the plant. If the customer does not have it, we extract it from the PLC whenever possible; if that cannot be done, the customer has to specify how the whole system works.
  3. New program, depending on the original PLC:
    • Siemens S5: from S5 (STEP 5) to S7 (STEP 7) and then to TIA Portal.
    • Siemens S7-300 (STEP 7): to TIA Portal.
    • Schneider: from PL7, Concept or Unity Pro to EcoStruxure Control Expert, if it stays with Schneider, or to TIA Portal.
    • Omron: to the CJ3M or CJ2M with CX-Programmer, or to TIA Portal.
    • Allen-Bradley (RSLogix 5 or RSLogix 500): to TIA Portal.
    • Mitsubishi, IDEC and others: to TIA Portal.
  4. Simulation tests. We program test modules in the PLC itself that simulate its inputs and outputs, so we can test all the logic and the screens before going on site.
  5. Review with the customer. We go through the documentation with the customer and present the tests carried out, for their approval before going into production.
  6. Replacement and commissioning. We replace the PLC, the screens and, if needed, the network during the shutdowns agreed with the plant, and carry out the commissioning.
  7. Final documentation. We hand over the commented program, the updated diagrams and the explanations the maintenance staff need. We keep a copy of the program and the documentation, and keep it up to date with any changes we make later.

What it includes

  • PLC and I/O, including ET 200SP distributed I/O.
  • HMI screens: from WinCC flexible, PanelView, Magelis or Omron to Siemens screens with WinCC in TIA Portal or WinCC Unified, to Beijer or Weintek screens, or to an Ignition SCADA.
  • Network: from Profibus to Profinet, and from legacy networks (Modbus Plus, DH+, SYSMAC LINK…) to Profinet, EtherNet/IP or Modbus TCP, in one go or in stages.
  • Pharmaceutical validation: URS, IQ and OQ documents, with GMP and 21 CFR Part 11.
  • ATEX zones: Turck ATEX I/O, and replacement of old barriers with new models or with ATEX I/O.
  • Electrical panel: adaptation of the existing panel or a new panel.
  • Support: after commissioning we continue to support the installation, with a fast response time.
  • SCADA: upgrade or migration to Ignition.

PLC migration projects in Barcelona

These are some of the PLC migrations we have carried out at plants in the province of Barcelona. We work mainly for pharmaceutical, chemical (including ATEX zones), flavours and fragrances, and water and waste treatment plants, in continuous production and with their own maintenance team. The list does not include them all and covers migrations only: we also carry out complete automation and SCADA projects, with the electrical control panels they need.

Sector and areaBeforeAfter
Pharmaceutical
Vallès Occidental
S7-300 with ProfibusS7-1500 with Profinet
Chemical
Vallès Oriental
Several TSX Premium and TSX Micro with PL7Modicon M340 with EcoStruxure Control Expert
Chemical
Vallès Oriental
TSX Premium and TSX MicroSiemens S7-1500
Waste treatment
Baix Llobregat
Two Omron PLCs: C200HG (18 modules) and CQM1 (10 modules)A single Omron CJ2M with three racks
Waste treatment
Baix Llobregat
Omron C200HSiemens ET 200SP CPU with 312 signals and Ignition SCADA in the cabinet
Waste treatment
Baix Llobregat
Omron CQM1 on the filter pressSiemens ET 200SP CPU with 66 signals, integrated into the SCADA
Water treatment
Vallès Oriental
IDEC PLCSiemens S7-1200
Metal foundry
Vallès Occidental
Siemens S5 and operator screenET 200SP CPU and Siemens screens with TIA Portal
Metal foundry
Anoia
Allen-Bradley SLC 5/05 and Omron screenSiemens S7-1500 with Profinet and Beijer screen
Metal foundry
Anoia
Omron C200HOmron CJ2 with Profibus, Profinet and ET 200S I/O
Metal foundry
Anoia
Omron CQM1Siemens S7-1500
Plastics extrusion
Osona
Siemens S5 and S7-300Siemens S7-1200

Frequently asked questions

How long will S7-300 spare parts be available?

Since 1 October 2025, Siemens has only sold the S7-300 as a spare part and in spare-part quantities, so it can no longer be used to expand an installation. Siemens expects to keep supplying spare parts until October 2033, but warns that it cannot guarantee this for every module, and it reserves the right to supply some only in exchange for the faulty part. If a CPU or a card fails and no spare is available, the plant stays down until it arrives.

What changes from the S7-300 to the S7-1500?

The S7-1500 is programmed with TIA Portal, has Profinet built into every CPU and is much faster. Most CPUs have a display showing status and diagnostics, and all of them include a web server and better program and access protection. For each S7-300 I/O card we find the most suitable equivalent in the S7-1500 range. And it is a current product, with Siemens spare parts and support.

Can an S5 program be converted to S7?

Yes. First we convert the program from S5 to S7 (STEP 7) and then move it to TIA Portal. But converting it is not enough: the operation has to be reviewed thoroughly and the code rewritten, because many S5 instructions have no equivalent in the new PLC. The I/O modules in the S5 racks are replaced with their equivalents in the new PLC.

What if we don't have a copy of the program?

This is very common: many plants do not have a copy of the PLC program, or the one they have is not the latest. That is why, whenever possible, we retrieve it from the PLC itself. And if the PLC is password-protected and nobody remembers the password, we have been able to find solutions on older PLCs such as the S7-300.

How long does the plant have to stop?

It depends on each case, and we study it in detail. If only the PLC is replaced and all the I/O runs over Profibus or Profinet, the migration can be done in a few days. If there are major electrical changes, the plant's shutdowns have to be used, such as the summer, Christmas or Easter shutdowns. If there is no long shutdown, it can also be done step by step, with smaller changes over several short stops.

What if something goes wrong at start-up?

We always have a rollback to the previous installation ready, although so far we have never had to use it. When we make the changeover, the program and the screens have already been tested and validated with the customer.

Can a STEP 7 project be moved to TIA Portal?

TIA Portal has a function for migrating STEP 7 V5.5 projects; projects from earlier versions are first opened in that version. However, when moving to S7-1500 the program has to be reviewed, because some S7-300 functions do not exist or work differently.

What about WinCC flexible screens?

We migrate them without any problems to WinCC in TIA Portal or to WinCC Unified, usually with current Siemens panels. Depending on the project, the migration involves more or less work.

Does the Profibus network have to be replaced?

Not always. Profibus is still manufactured and the S7-1500 can work with Profibus. The usual approach is to use the migration to move to Profinet, in one go or in stages.

Contact

If you have a discontinued PLC, write to us using this form and we will plan it with your team. We review the installation and propose the migration and the schedule, so that the changeover is made during the plant's scheduled shutdowns. We are in Sabadell (Barcelona) and work for plants in the Vallès, the Barcelonès, the Baix Llobregat, the Alt Penedès and the Anoia.

Tell us which PLC you have and what you need and, if you can, attach photos of the PLC and its modules.

Up to 3 PDF, Word or image files. Maximum size per file: 5 MB.
Write to us